1) 16 men can complete the job in 8 days, then in how many days the work will get complete if employ 8 more people.
Explanation:
16 men can complete in 8 days
1 man can do in (8 x 16) days
8 more people, now the total number of people = 8 + 16 = 24
24 men will take (8 x 16)/24 = 16/3 days