1) Hemal can complete a work in 8 days, what percentage of the work would be completed in 2 days ?

Explanation:

Lets considers 8 days as 100 %, the work gets done So 4 days is 50 % where half of the work is done So when Arun has worked for 2 days, then => (2/8) x 100 = 100/4 = 25 %